Project Profiles
    Power Generation
   Kazzinc New Metallurgy

   /images/GPGimages/ProjectImages/kazzincNewMetallurgy.jpg Location: Ust – Kamenogorsk, Kazakhstan
Customer: Extrata Technology Pty Limited, Australia
End User: Kazzinc Metallurgical Complex
Start-up Year: 2010
Capacity: Saturated steam 8 kg/s ( Pb-WHB ) and 6.5 kg/s ( Cu-WHB )
Unit Type: 1 x WHB for Cu ISA-smelt Furnace
            1 X WHB for Pb ISA-smelt Furnace
FW Scope: Design & Supply for WHB and key auxiliary equipment

   Project Features:
   New copper smelter and refinery. In addition, the lead smelting process upgraded.
   WHB primary performance is cooling of the hot process gas and heat recovery
   Air cooled condensing delivered as optional equipment for heat disposal